Work still progressing on extension, track bed cleared from Broadway to Childswickham bridge, welding ongoing Stanton area, Laverton bridge cut up 27/03/08  GWR Permanent Way 2008 Progress  (2894)
Double headed PW train on Stanway viaduct 18/03/06  GWR Permanent Way 2006  (2083)
12 rails down past   GWR Permanent Way 2006  (2040)
Stanway Viaduct looking north end of day 29/10/05  GWR Permanent Way 2005  (1872)
North of viaduct 26/11/05, this is as far as we go until March 06  GWR Permanent Way 2005  (1855)
A start is made on the replacement of Laverton bridge 16/10/09  GWR Permanent Way 2009 Progress  (1752)
A slight buckle in the heat on newly welded section (caused by parking train far side of buckle) 17/06/06  GWR Permanent Way 2006  (1372)
Stanway Viaduct looking south 29/10/05  GWR Permanent Way 2005  (1252)
View south off Stanton Rd Bridge (note newly delivered ballast) 24/06/06  GWR Permanent Way 2006  (1236)
10 A view from Stanton Road bridge with the loaded dogfish 27/07/06  GWR Permanent Way 2006  (1232)
Most Recent Collections
8th Feb 2010GWR Permanent Way 2010 Progress
2010 collection of GWR Permanent Way team weekly progress.

For previous year 2009, see GWR Permanent Way 2009 Progress.
9th Jan 2010GWR P Way Rogues Gallery
A selection of "dubious" individuals that attend the GWR PW gang and some are occasionally caught working!!! Beware someone has a diggie camera aimed at you!!!
19th Dec 2009GWR Permanent Way 2009 Progress
The ongoing Permanent Way work undertaken by the volunteer gang at The GWR.

Special Projects have a separate collection, eg fitting Toddington North turnout.

For 2008 see collections below.
10th Jul 2009
to 12th Jul 2009
2009 Summer Diesel Gala
A quick visit to Winchcombe on Friday lunchtime to catch 08927 to Toddington and..........
later, post work, a trip to CRC and back behind 33109 and 47376.

More tomorrow from Todd yard?

And a little foray out on Sunday as well.......
14th Mar 2009Toddington North Remodelling
Update on the installation of the E15 turnout and upgrading of all other trackwork to allow passenger traffic to access the extension to Broadway.
27th Dec 2008GWR Permanent Way 2008 Progress
GWR Permanent Way Department work for 2008, a collection on the progress of the Pway heading for Broadway (or not!), interlaced with essential maintenance work on the existing running lines. For the year 2007 see collection below.
25th Oct 2008
to 26th Oct 2008
GWR 2008 Autumn Diesel Gala
Autumn Diesel Gala Sunday only for this Gala!
5th Jun 20082008 GWR Summer Diesel Gala
A few pictures of the Summer Gala preparations
4th Apr 2008
to 6th Apr 2008
GWR Spring Diesel Gala 2008
First GWR diesel gala of 2008, viewed from the inside of the buffet cars!? With the odd shot taken lineside whilst on PWay duties, skiving off work and filling the car up with diesel!
Gala punctuated with hot sun (Friday), cold wind with rain, hail & sun (Saturday) and snow&sun (Sunday).
23rd Feb 2008Turnout Installation Work Week @ CRC
A work week was organised to fit a turnout at CRC to access the second siding. We have had enough of dragging the rail backwards and forwards with the JCB!
3rd Feb 2008GWR Pway Away Day to Help SVR Pway
A small gang from GW Pway join forces With the SVR Pway Gang to help reinstate trackwork at Sterns after the infamous 2007 flood.
31st Dec 2007GWR Permanent Way 2007
Gloucester Warkwickshire Railway Permanent Way Gang 2007 pictures, was mainly the push toward Broadway but now intermingled with some essential maintenance, giving a broad background of our day-to-day duties during 2007. For 2006 see collection below.
27th Oct 2007PWay and Clearance Gang at Stanton Fields
PWay and the Cutting Gang combine forces at Stanton Fields to clear Cotswold bank to enable imminent grading and sleeper laying.
Also some pictures when the area was cleared last time which shows once cleared it should be flailed regularily otherwise we are wasting our time!
30th Mar 2007
to 1st Apr 2007
GWR Spring Diesel Gala 2007
A quick view of some of the goings on!
[ More collections ]
Most Recent Photo

Contract work starts on removing most of the joints in tunnel, all "crippled" ends cut off and rails dragged up with JCB for welding or redrilling, Greet Tunnel 08/02/10
Adverts
Welcome
GWR Permanent Way Work. The push toward Broadway including essential maintenance of the existing running line to Cheltenham.

Plus some older BR shots, mainly featuring BR BLUE livery!
Top Photo

Work still progressing on extension, track bed cleared from Broadway to Childswickham bridge, welding ongoing Stanton area, Laverton bridge cut up 27/03/08
(2894 hits)
GWR Permanent Way 2008 Progress
Gallery Stats
Hits (today):36
Hits (this week):684
Hits (this month):2551
Hits (this year):14346
Hits (all-time):470835
Collections:26
Links
  • Andy Manleys Broadway Extension Site
  • Avonvale MES Railway
  • Cotswold Mainline Diesels
  • GWR Clearance Gang
  • GWR Offical Web Site
  • P.Fuller's PWay Photos
  • Fotopic.Net
  • Leave a Message
    Click here
    to get in touch!
    Notify Me!
    Enter your email address to be contacted when this gallery is updated:
    Search Gallery
    Find:  
    Photos   Collections